Hi
We are using 4760 r-4.2 and OXE 7.1( for 10 nodes), recently we have upgraded one of the node to OXE r-10 now, 4760 r-4.2 failing to synchronize that node with rel-10. It shows
[8/1/2012 12:04:18 AM] Scheduler: The job is started.
[8/1/2012 12:04:25 AM]
New Status : Establishing IP/X25 connection
[8/1/2012 12:04:35 AM]
New Status : IP/X25 connection established
[8/1/2012 12:04:35 AM]
New Status : MIB Synchronization
[8/1/2012 12:04:35 AM] Target: Lengthy operation protected by timer 02:15:00
[8/1/2012 2:19:46 AM]
Error : Successful Operation - No Error
[8/1/2012 2:19:46 AM] Target: Some PCX systems have not been fully loaded!
[8/1/2012 2:19:46 AM] Scheduler: Job failed.
help needed. is it because of that timer and if it is then where and how can i change this timer? if not timer then help me with expart advose,please.
Thanks.